The Summer Shutdown Playbook: Turn Quiet Weeks Into Years of Uptime

Jul 10, 2026
Industry News
The Summer Shutdown Playbook for Press Maintenance | Sutherland Presses
Sutherland Presses logo
Press Maintenance | Shutdown Planning |July 2026

The Summer Shutdown Playbook. Turn Quiet Weeks Into Years of Uptime.

The Short Version

Across North America, plants are heading into their summer shutdown windows. A stopped press is the one maintenance opportunity a running production schedule never gives you. Here is how to spend that window well: a PMP inspection before the shutdown to build the work list, red items corrected while the press is down, upgrades like I-PRESS® control retrofits installed in the same window, and operators trained before the ramp back.

Every pressroom knows the feeling of a maintenance list that only grows. Gib adjustments that need a stopped press. A clutch and brake inspection that keeps sliding right on the calendar. A control retrofit everyone agrees on but nobody can schedule. During production, none of it fits.

Then the shutdown arrives, and the most common mistake is walking into it without a plan. Two weeks disappear into whatever breaks loose first, and the press starts back up with the same list it went down with.

Before and after of an I-PRESS control retrofit replacing an obsolete push button panel on a Sutherland press
The Shutdown Window  |  Inspect, Correct, Upgrade, Train
11
Press Systems in the PMP Framework
107M
Strokes Without Unplanned Downtime, One Customer's Proof
2
Typical Shutdown Weeks. Plan Every Day.
The Playbook

Four Moves. In This Order.

01

Inspect Before the Shutdown

Run a PMP inspection while the press is still in production. The red, yellow, green report becomes your shutdown work list, with photos, so parts and people are ready on day one.

02

Correct the Red Items

Stopped press work first: clutch and brake inspection, gib and guide adjustment, connection point checks, hydraulic fluid sampling, and lubrication line verification.

03

Upgrade in the Same Window

A shutdown is the natural window for an I-PRESS® retrofit. Replace obsolete relay panels with modern Allen Bradley or Omron based controls without stealing a single production day.

04

Train Before the Ramp

New controls should never meet their operators on the first production morning. Use the browser based I-PRESS® simulator to build screen time before the press restarts.

Why the Sequence Matters

The order is the playbook. Inspecting first means the shutdown starts with a prioritized work list and parts on the shelf, not a discovery process. Correcting before upgrading means the retrofit lands on a mechanically sound press. Training last means the restart is a ramp, not a rescue.

The payoff for this discipline is not theoretical. One Sutherland customer has run 107 million strokes over five years without unplanned downtime, built on exactly this rhythm: inspect on schedule, correct what the inspection finds, and never let the work list winter over to next year.

Before Your Shutdown

Book the Inspection First.

Tell us your shutdown dates and we will work backward: PMP inspection scheduled ahead of them, findings and parts lined up, and retrofit options scoped so the window does double duty.

Shutdown Season  |  Summer 2026
Sutherland Presses  |  1-310-453-6981  |  SutherlandPresses.com

< BACK TO SUTHERLAND NEWS

Sutherland Presses

The Summer Shutdown Playbook: Turn Quiet Weeks Into Years of Uptime

The Summer Shutdown Playbook for Press Maintenance | Sutherland Presses
Sutherland Presses logo
Press Maintenance | Shutdown Planning |July 2026

The Summer Shutdown Playbook. Turn Quiet Weeks Into Years of Uptime.

The Short Version

Across North America, plants are heading into their summer shutdown windows. A stopped press is the one maintenance opportunity a running production schedule never gives you. Here is how to spend that window well: a PMP inspection before the shutdown to build the work list, red items corrected while the press is down, upgrades like I-PRESS® control retrofits installed in the same window, and operators trained before the ramp back.

Every pressroom knows the feeling of a maintenance list that only grows. Gib adjustments that need a stopped press. A clutch and brake inspection that keeps sliding right on the calendar. A control retrofit everyone agrees on but nobody can schedule. During production, none of it fits.

Then the shutdown arrives, and the most common mistake is walking into it without a plan. Two weeks disappear into whatever breaks loose first, and the press starts back up with the same list it went down with.

Before and after of an I-PRESS control retrofit replacing an obsolete push button panel on a Sutherland press
The Shutdown Window  |  Inspect, Correct, Upgrade, Train
11
Press Systems in the PMP Framework
107M
Strokes Without Unplanned Downtime, One Customer's Proof
2
Typical Shutdown Weeks. Plan Every Day.
The Playbook

Four Moves. In This Order.

01

Inspect Before the Shutdown

Run a PMP inspection while the press is still in production. The red, yellow, green report becomes your shutdown work list, with photos, so parts and people are ready on day one.

02

Correct the Red Items

Stopped press work first: clutch and brake inspection, gib and guide adjustment, connection point checks, hydraulic fluid sampling, and lubrication line verification.

03

Upgrade in the Same Window

A shutdown is the natural window for an I-PRESS® retrofit. Replace obsolete relay panels with modern Allen Bradley or Omron based controls without stealing a single production day.

04

Train Before the Ramp

New controls should never meet their operators on the first production morning. Use the browser based I-PRESS® simulator to build screen time before the press restarts.

Why the Sequence Matters

The order is the playbook. Inspecting first means the shutdown starts with a prioritized work list and parts on the shelf, not a discovery process. Correcting before upgrading means the retrofit lands on a mechanically sound press. Training last means the restart is a ramp, not a rescue.

The payoff for this discipline is not theoretical. One Sutherland customer has run 107 million strokes over five years without unplanned downtime, built on exactly this rhythm: inspect on schedule, correct what the inspection finds, and never let the work list winter over to next year.

Before Your Shutdown

Book the Inspection First.

Tell us your shutdown dates and we will work backward: PMP inspection scheduled ahead of them, findings and parts lined up, and retrofit options scoped so the window does double duty.

Shutdown Season  |  Summer 2026
Sutherland Presses  |  1-310-453-6981  |  SutherlandPresses.com

Heading

Heading

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

back to news >

SUTHERLAND CLIENTS

REQUEST A QUOTE